Prox Card reader installed on Northbound Tolls

Prox Card readers installed on northbound toll booths at Sault Ste. Marie International Bridge

December 12, 2014 – Installation of “Prox” toll card readers on the new northbound booths is being finished as part of the Sault Ste. Marie International Bridge Toll Plaza Reconstruction project.

IMG_6138“Our customers really like the convenience of the card readers and automated lanes,” said Peter Petainen , International Bridge Administration (IBA) chief financial officer. “Despite delays due to weather, we are pleased to report the first reader and automated gate will be operational on Monday, Dec. 15.”

The outside northbound lane to Canada will be opened to Prox customers beginning Monday, (more…)

Continue ReadingProx Card reader installed on Northbound Tolls

Portion of new toll plaza to be opened at Sault Ste. Marie International Bridge

October 17, 2014 — Two of the six planned new toll booths at the International Bridge are in place and will be open for toll collection from three new lanes beginning as early as 11 a.m. Monday, Oct. 20.IMG_5564

“The pavement, utility tunnel, and toll booths on the eastern portion of the toll plaza will be completed on schedule and we can begin toll collection from two booths to serve three lanes,” said project manager Karl Hansen.

Early in the week, the two new northbound toll lanes will open and process traffic as the last temporary northbound toll booth and lane are removed. By midweek, (more…)

Continue ReadingPortion of new toll plaza to be opened at Sault Ste. Marie International Bridge

Toll Plaza update: IBA prepares for new booths and toll software

Fast Facts:

  • The 2-year, 8.9-million-dollar Toll Plaza construction project continues at the Sault Ste. Marie International Bridge.
  • A recent survey shows traffic impacts have been minimal.
  • The IBA’s goal is to get two permanent toll booths installed and operational in October.
  • New enhanced toll software is slated to be installed in early 2015.

 Sept. 11, 2014 — The International Bridge Administration (IBA)  is breathing a collective sigh of relief as the summer peak traffic season progresses without major congestion issues from the 2-year, 8.9-million-dollar Toll Plaza construction project.

“We are very pleased with the safe and smooth traffic flow through the toll plaza project,” said IBA General Manager Phil Becker. “A lot of planning went into the temporary (more…)

Continue ReadingToll Plaza update: IBA prepares for new booths and toll software